Breaking Down the Work-in-Process Schedule

An in-depth and clear understanding of the WIP components is an essential tool to ensure any potential detriments are addressed immediately, thereby reducing any potentially negative impact on a contractor’s financial statements.
By Robert Mercado and Megan Moriarty
September 3, 2020
Topics
Business

The financial statements of construction contractors are based primarily on estimates. The crucial question when analyzing the statements is how reliable those estimates prove to be. In an effort to provide such reliability, a contractor’s work-in-process (WIP) schedule should be prudently examined, as the WIP narrates the health of these statements.

While the format of the WIP can vary contractor to contractor, it provides information on jobs from inception to date, in addition to as of and for the current reporting period. The following is an example of a work-in-process schedule

Understanding the WIP

Before any analysis can take place, it’s important to understand the various components of the WIP. The following provides details on each WIP component.

Total Contract Price

Total contract price is not as simple a concept as it sounds. To the contrary, the total contract price can be comprised of multiple items. These items include the following.


Total Estimated Cost of Revenue Earned (ERC)

The ERC is one of the most important items on the WIP. It is also the most difficult to calculate. If this amount is calculated incorrectly, it could compromise the contractor’s profitability. ERC is the sum of all anticipated costs that will be incurred on the project from inception through completion. It includes all direct contract costs along with the indirect costs that will be allocated to the project. The ERC should be reviewed on a regular basis, usually monthly, to ensure that the contract is progressing as projected.

Job-to-Date Contract Revenue Earned (RE)

The percentage of completion method (POC) is a method to calculate the revenue earned on a project. Most contractors use the cost-to-cost method of POC to calculate the RE. The cost-to-cost method compares the job-to-date cost of revenues earned divided into the ERC, which calculates the percent complete based on cost incurred. This percent complete amount is then multiplied by the total contract price. As an example from above, Project A incurred $450,000 of JTD cost of revenue, earned which is divided into the ERC of $1,250,000. This equates to 36% complete. The contract price is multiplied by the 36% complete to come to a RE of $540,000. This number represents the RE based on POC.

Job-to-Date Cost of Revenue Earned (CRE)

All costs incurred, whether direct or indirect, should be reported on each project. Direct costs can include materials, direct labor, subcontracting and equipment rental. Indirect costs are allocated to a project based on a systematic approach, such as a percentage of direct labor. Indirect costs can include project management, indirect labor (i.e., warehouse labor), depreciation, auto and truck, and repairs and maintenance. It is imperative that costs comprising a project are relative to the cost included in the ERC. Costs charged to a project that are not included in the ERC may cause the RE and gross profit reported to be incorrect.

Accrued Loss
When calculating POC, the job-to-date gross profit recognized is based on the percent complete of the project. If a loss is anticipated, the amount of the loss that would be earned is based on the percent complete. As an example from above, Project B is expected to have a $150,000 loss. Based on cost incurred, Project B is 32% complete. The loss earned as of that moment would only be $48,000. Since Generally Accepted Accounting Principles require that the entire loss be earned as of the moment a loss is anticipated, this would result in a shortfall of $102,000. An accrued loss is added to the project in order to account for the additional loss not captured through POC.

Job-to-Date Billing

In most industries, the amount billed to a customer is considered revenue earned. However, for contractors, revenue earned is based on POC, not on the amount billed. The job-to-date billing amount will be the total requisitioned by the customer, including retainage held (also known as the “total complete and stored to date”) on the requisition.

Estimated Cost to Complete

This is calculated by subtracting the CRE from the ERC. As the name suggests, this amount represents the balance of cost left to complete on a project.

Costs and Estimated Earnings in Excess of Billings (CIE)

CIE, also referred to as underbillings, is considered a current asset. CIE is the amount of RE in excess of the amount billed on a project. CIE could represent poor billing practices, an inability to bill for work performed due to milestone not reached, incurred cost on an unapproved change order deemed unbillable or an overstatement of estimated gross profit on the project. Underbillings are not normal practice and should be considered a risk to the contractor. All significant underbillings should be investigated for origin and accuracy.

Billings in Excess of Costs and Estimated Earnings (BIE)

BIE, also referred to as overbillings, is considered a current liability. BIE is the amount of billing in excess of the RE on a project. BIE represents good billing practice, representing potential front-end loading of profit in earlier project stages based on the schedule of values, or deferred profit.

Ratio Analysis

The following are several ratios relating to the WIP schedule. Systematic analysis of these ratios will ensure that financial reporting is accurate based on project estimates.

Contract Gain/Fade

Contractors should be analyzing profitability on a job-by-job basis to ensure that the anticipated gross profit at completion remains close to the original estimate. Contractors should watch for projects that have a fade of the expected gross profit. If gross profit expected at completion begins to decrease, it is important to strategize priorities in an effort to restore the original estimated profit.

Underbillings-to-Equity

The underbillings-to-equity ratio is calculated as a percentage of CIE divided into stockholder’s equity. It is the percentage of the contractor's net worth represented by work performed but not yet billed. A ratio in excess of 20% is considered unusual. The higher the percentage, the greater a contractor’s equity is, based on an estimate of project cost incurred that could not be billed to a customer.

Underbillings-to-Working Capital

Underbillings-to-working capital is calculated as a percentage of CIE divided into working capital. This ratio represents the portion of the contractor's working capital (the difference between current assets and current liabilities) comprised of underbillings. A ratio in excess of 25% is considered unusual. The higher the percentage, the more a contractor’s working capital is based on an estimate of cost incurred on a project that could not be billed to a customer.

Overbillings-to-Cash

This is calculated as of percentage of BIE divided into cash and cash equivalents. The amount of cash in the bank represents a ratio of BIE. All overbilled amounts should be represented by cash in the bank. Therefore, an acceptable ratio of cash to overbillings is generally 1 or higher. The concern related to this ratio is overbilling on one project to cover the cost, or worse, the loss incurred on another project. If cash is borrowed for another project, the contractor may not have the cash to pay expenses on the overbilled project.

Total Job Borrow

This is the total CIE from total BIE. This indicates the net percentage-of-completion adjustment. A positive number represents a net overbilling. This indicates that the contractor has bid a job where the customer will assist the contractor in financing. A negative number represents a net underbilling, which is considered unusual. Net underbillings may indicate poor billing or bidding practices or may also indicate overly aggressive profitability forecasts.

Total Backlog

Total backlog is the total contract price on open projects less RE on the open projects. This analysis assists the contractor in determining if additional future work is needed to maintain current volume.

Total Backlog Gross Profit

Having a healthy backlog is important only if it carries a profit. The backlog gross profit is calculated by comparing the estimated total gross profit on open projects less the job-to-date gross profit. A good rule of thumb for contractors is that the backlog gross profit should cover at least 50% of the contractor’s general and administrative expenses for the following year. If the backlog is below this threshold, the contractor could have a difficult time meeting the financial requirements of the coming year.

Conclusion

An in-depth and clear understanding of the WIP components is an essential tool to ensure any potential detriments are addressed immediately, hence reducing any potentially negative impact on a contractor’s financial statements.

by Robert Mercado

Robert Mercado, CPA, CCIFP, is based in Marcum’s New Haven, Conn. Office, where he specializes in conducting, reviewing and analyzing financial information for construction contractors, manufacturers and service corporations. Marcum LLP’s Construction Services group provides audit, consulting, and taxation services to clients ranging from start-ups to multi-billion-dollar enterprises. Marcum LLP's Construction Services group provides audit, consulting, and taxation services to clients ranging from start-ups to multi-billion-dollar enterprises and publishes the annual Marcum National Construction Survey, the quarterly Marcum Commercial Construction Index, the Marcum PAS Contractor Compensation Quarterly, and the annual Marcum JOLT Survey Analysis of construction employment trends--and presents an ongoing series of industry summits and technical webinars focused on the unique needs of construction contractors.

 

Related stories

Business
ABC Members Invested $1.6 Billion To Upskill 1.3 Million in Construction Workforce Education Cover Art

ABC Members Invested $1.6 Billion To Upskill 1.3 Million in Construction Workforce Education

By ABC
ABC released its 2024 Workforce Development Survey and found investments into leadership, health and safety education were up from 2022.
Business
Top Three Trends That Will Continue to Impact Construction Through 2024 Cover Art

Top Three Trends That Will Continue to Impact Construction Through 2024

By David DeSilva
The second half of 2024 is likely to present the same problems to the construction industry—supply-chain issues, labor shortages and more—but you can approach them with different solutions.
Business
Busting Major Alternative-Lending Myths Cover Art

Busting Major Alternative-Lending Myths

By Warren Miller, CFA
Unique problems require unique solutions. In construction, that means certain projects can require alternative methods of financing.