On most commercial projects, the site contractor is the first trade on the job and one of the last asked for input. Mechanical, electrical and envelope trades are routinely brought into design-assist. The small excavation or hardscape firm usually gets a bid set a week or two before bids are due and a lump-sum form to fill out.
That sequence leaves money on the table. Site grades have to tie together finished floor elevations, accessible routes and drainage for the entire building. The ground is also where many of a project’s surprises live: rock, water, unsuitable soil and grades that don’t tie together. A few hours of a site contractor’s time before bid day can prevent change orders that surface in the second week of construction, when the excavator is already onsite.
Small site and hardscape subcontractors will rarely be the first names a general contractor calls for preconstruction help. But they can add outsized value in three areas: catching grading and drainage conflicts, turning design intent into buildable details for walls and pavements, and producing quantity takeoffs that make bids comparable.
Catching Grading and Drainage Conflicts
Civil, architectural and landscape drawings are often produced by different firms on different schedules, and the conflicts show up where those drawings meet the ground. A site contractor reviewing a bid set with construction in mind will typically check:
- Doors against grades: Architectural finished floor elevations should match civil spot grades at every exterior door. A mismatch of a few inches can mean an added step, a ramp or a rebuilt walk.
- Accessible routes: Under the 2010 ADA Standards for Accessible Design, a walking surface on an accessible route that runs steeper than 5% becomes a ramp, with the handrails and landings that come with it; and cross slope can’t exceed 1:48, about 2%. Tight sites and existing grades often make those numbers hard to hit and the fix is cheaper on paper than in concrete.
- Drainage away from the building: The International Building Code requires ground next to a foundation to slope away at 5% for at least 10 feet and impervious surfaces within 10 feet to slope away at 2%. Walks, patios and planting beds tucked against a building frequently fall short.
- Storm pipe inverts: Following each run from structure to outfall confirms that the pipe has cover, has fall and clears water, sewer and electrical crossings.
- Wall locations: A retaining wall drawn on a property line leaves no room for its footing, drainage aggregate or reinforcement.
Each conflict caught at this stage becomes a question to the design team before bid day instead of a request for information after award.
Turning Intent Into Buildable Details
Many civil sets show a segmental retaining wall as a line with a top and bottom elevation. A site contractor can turn that line into a layout the crew can build: wall elevations with step-downs into grade, reinforcement lengths, drainage aggregate and outlets, and the courses buried below grade.
That review also flags the point where a wall changes category. The International Building Code exempts from a permit a retaining wall 4 feet or less in height, measured from the bottom of the footing to the top of the wall, unless it supports a surcharge. Taller walls and walls holding up a parking lot, driveway or structure, typically need a permit and an engineered design. Knowing where that line falls before bid day keeps an engineering fee and a permit from surprising the owner later.
Pavements deserve the same attention. Base thickness, compaction targets, transitions between concrete and asphalt, and edge restraint for pavers are often covered by a general note or a detail that doesn’t fit the site. The subcontractor doesn’t replace the engineer. The value is in flagging what the engineer needs to finalize while changes are still free.
Takeoffs That Make Bids Comparable
Site bids are notoriously hard to level because lump sums hide different assumptions. One bidder may carry imported fill for a building pad while another assumes on-site material will work. One may include stripping 6 inches of topsoil while another carries 12 inches.
A takeoff with stated assumptions solves that problem. A useful site quantity sheet lists cut and fill volumes and the shrink or swell factor applied to them, topsoil stripping depth, stone and base quantities by use, and unit prices for undercut, rock and extra stone. It also lists erosion and sediment control items and who owns the paperwork. In Pennsylvania, earth disturbance of 5,000 square feet or more requires a written erosion and sediment control plan, and disturbance of 1 acre or more requires a National Pollutant Discharge Elimination System permit for construction stormwater.
With that sheet in hand, a general contractor can compare three bids on the same basis and see exactly where the numbers differ.
What General Contractors Should Ask For
During preconstruction, general contractors can ask site and hardscape subcontractors for:
- A marked-up plan review with questions, submitted before bid day
- A quantity sheet with assumptions, not only a lump sum
- Unit prices for undercut, rock and additional stone
- Sequence and durations for the site package, including mass grading windows and erosion control phasing
- Long-lead items such as precast structures, wall block and specialty pavers
- Clear inclusions and exclusions for permits, testing, layout and dewatering
What Subcontractors Should Charge For
Budget pricing and answering questions are part of the cost of chasing work. Deeper work is a service and should be treated as one. Layout drawings, wall reinforcement layouts, alternative pavement sections, value-engineering redesigns and site visits with test pits take real hours from people who could otherwise be running work.
A fixed preconstruction fee, credited against the contract if the subcontractor is awarded the job, is fair to both sides. When a design needs an engineer’s stamp, the subcontractor can coordinate with a licensed engineer and carry that cost as a stated pass-through. Both parties should also agree that the subcontractor’s drawings and quantities won’t be shared with competing bidders. Without that protection, the best preconstruction work in the market becomes free help for the lowest bidder.
The Payoff
The site package is usually a small share of the contract value but carries a large share of the schedule risk, because everything else is built on top of it. Bringing the site contractor to the table a few weeks earlier and paying for the work that goes beyond a bid is one of the least expensive forms of risk management available to a general contractor.