Risk
Business
Legal and Regulatory

Hurry Up and Wait: Pacing and Concurrent Delay in Schedule Disputes

When critical path activities are delayed by the owner (or another party), contractors will sometimes “pace,” or slow down, other activities to match the owner-caused delay. What should contractors do to preserve their rights to obtain more than a simple time extension?
By William E. Underwood
April 10, 2020
Topics
Risk
Business
Legal and Regulatory

When critical path activities are delayed by the owner (or another party), contractors will sometimes “pace,” or slow down, other activities to match the owner-caused delay. After all, why should the contractor hurry up and wait?

Regardless of intent, paced activities can often appear as concurrent delays on a project’s schedule. And all too often, contractors fail to contemporaneously document their efforts to pace work, thereby creating additional roadblocks to the recovery of delay damages.

What should contractors do to preserve their rights to obtain more than a simple time extension?

As a basic matter, most contracts allocate responsibility/liability for a schedule delay to the party that caused the delay. For example, if an owner is contractually required to provide equipment for a contractor to install, then the owner bears responsibility for any delays caused if the equipment is delivered late. If, however, the contractor was also behind schedule on other activities during this time and the project would have been delayed regardless of the owner’s late deliveries, then the delay is concurrent. And the contractor will generally be entitled to only an extension of time, and no other monetary relief.

But what if the owner notifies the contractor that the equipment delivery will be late and the contractor elects to slow down, or “pace,” its other work so that it will complete these unrelated tasks at or near the new equipment delivery date?

A cursory review of the project schedule would then appear to show a concurrent delay: both the contractor and owner are now set to complete unrelated activities beyond their originally planned durations, thereby concurrently delaying the project.

To Pace or Not to Pace

A contractor has a few ways to preserve its contractual and legal rights to monetary relief in light of the owner’s delay. An important initial step is to ensure that the contractor actually has the right to pace its work. For example, many contracts contain a standard requirement that the contractor “diligently pursue the work.” So, it is important to reread the contract and note all relevant provisions impacting a decision to pace work.

That being said, many courts and boards have determined that contractors do not need to zealously adhere to a disrupted schedule. As a result, many jurisdictions allow contractors to intentionally slow down work in the event of a non-contractor-caused delay. But this is not always the case, and it is critical to understand the specific state and federal laws, rules and regulations governing the project. Failure to do so could result in self-inflicted wounds brought on by impermissible pacing.

What’s Up, Doc?

Another critical step is to document, document and document some more. True pacing is a conscious, voluntary, contemporaneous decision to slow down work, but it may not always look that way to a third party (such as an arbitrator or expert) conducting an after-the-fact review of project schedules and correspondence. Therefore, a contractor should be unyieldingly fastidious in contemporaneously documenting its election to slow down.

Actual notice is the preferred method—a written communication to the owner plainly identifying the non-contractor-caused delays, the activities to be paced and the new anticipated completion dates for those activities. Some contractors will even go so far as to submit a formal “pacing plan” that contains schedule updates, a detailed accounting of the paced activities and any other relevant information. Nevertheless, it is always important to check the contract to identify all relevant notice requirements—or possibly even specific notice requirements in the event a contractor elects to pace its work—and then adhere to those requirements. In other words, compliance is key.

But even if a contractor fails to provide actual notice, there may be other avenues to escape the label of concurrent delay. Constructive notice is one such avenue. Under a theory of constructive notice, a contractor can claim that although it may not have provided actual notice, the owner nonetheless knew that the contractor was pacing its activities. This is not an ideal method, and will likely lead to claims that the contractor is simply using pacing as an after-the-fact fiction to get delay damages; additionally, the contractor will likely need strong expert analysis to bolster its claims of pacing, but it is better than no method at all.

Pacing is not without risk. The owner (or other delaying party) may unexpectedly erase all or part of an anticipated delay, thereby making the contractor’s paced activities theoretically delayed. In that case, there will almost certainly be a dispute regarding the permissibility and impact of the contractor’s election to pace its work.

Consider another risk that, in the event of a future dispute, the paced activities will be seen as a concurrent delay, which is when notice and contemporaneous documentation become vitally important.

There is debate within the industry that contractors should not be entitled to full delay damages for paced activities because in theory, pacing can mitigate these damages. Therefore, if a contractor seeks full compensation for the delays on the project, it could be overcompensated for the harm it actually incurred. This overcompensation argument can serve as a roadblock to the full recovery of damages.

Thus, pacing can be an effective—but risky—technique. Contractors must take the necessary steps to preserve their right to future recovery.

by William E. Underwood

William represents a broad array of domestic and international clients, including owners, general contractors and design-build contractors, with issues related to large industrial and infrastructure construction projects located in the United States and abroad. He has represented clients in a number of United States and international dispute forums, including state and federal courts, federal boards of contract appeals, AAA arbitration, ICC arbitration and LCIA arbitration. 

William provides legal advice to clients throughout the entire life cycle of a project, from inception to completion. William’s experience ranges from representing owners and contractors involved in high stakes disputes regarding billion-dollar projects to advising clients on issues related to contract drafting, contract negotiation, risk mitigation and overall project management. 

While in law school, William served as a student attorney in the Washington and Lee Community Legal Practice Center and represented the school in the ABA Regional Client Counseling Competition. He also served as an articles editor for the Washington and Lee Journal of Civil Rights and Social Justice and authored a published student note on Fourth Amendment search and seizure law.

Related stories

Risk
Executive Insights 2024: Leaders in Surety
By
Experts in surety reveal their industry insights.
Risk
Calculating the True Cost of Underinvesting in Construction Health and Safety
By James Alexander
Research from the Construction Safety Research Alliance aims to set a global standard for safety, efficiency and finance at construction companies.
Risk
Mitigating Four Major Risk Factors in the Construction Industry
By Julia Holden Davis
ESG, inflation, the supply chain and weather pose major risks to the construction industry. Knowing them is the key to understanding and mitigating them.

Follow us




Subscribe to Our Newsletter

Stay in the know with the latest industry news, technology and our weekly features. Get early access to any CE events and webinars.