Closeout: Pour It on Thick

by | Sep 30, 2024

Come to Miami for the Waldorf Astoria, stay for the 36-hour concrete pour.

several cranes erected over the concrete foundation at the new Waldorf Astoria in Miami

PROJECT | Waldorf Astoria Hotel & Residences, Miami

GENERAL CONTRACTOR | John Moriarty & Associates

BUDGET | 8 million

SCOPE | 1,400 trucks initiated a record-breaking uninterrupted 36-hour concrete pour, delivering 13,500 cubic yards of concrete for the foundation of the Waldorf Astoria Hotel & Residences Miami which, when completed in 2027, will stand as the tallest building south of New York City

TIMELINE | Fri., June 14, 2024 – Sun., June 16, 2024

Author

  • Construction Executive

    Construction Executive, an award-winning magazine published by Associated Builders and Contractors, is the leading source for news, market developments and business issues impacting the construction industry. CE helps its more than 50,000 print readers understand and manage risk, technology, economics, legal challenges and more to run more profitable and productive businesses.

    View all posts https://constructionexec.com/ |