PROJECT | Main Street Terminal 1, Port of Beaumont, Beaumont, Texas
GENERAL CONTRACTOR | McCarthy Building Companies
BUDGET | million
SCOPE | Demolition of a collapsed 100-year-old dock and construction of a new general cargo dock—1,200 feet wide, 130 feet long and composed of concrete piles, cast-in-place concrete caps and beams, pre-cast concrete deck panels and a concrete topping slab
TIMELINE | February 2022 to May 2024
Author
-
Construction Executive, an award-winning magazine published by Associated Builders and Contractors, is the leading source for news, market developments and business issues impacting the construction industry. CE helps its more than 50,000 print readers understand and manage risk, technology, economics, legal challenges and more to run more profitable and productive businesses.