Michael W. Bennett
Vice President
Cianbro
Pittsfield, Maine
Cianbro’s disaster recovery plan is a documented process that includes step-by-step procedures to restore the company’s business to “normal” operations following a disaster. It includes who to contact, identifies our internal emergency response team and details the specific plans for each facility. The program also includes annual training and drills.
First and foremost, it begins with safety. We must ensure that our team, business partners and clients have a safe work environment to return to. We expect a thorough hazard assessment be completed for each disaster and a plan on how we will safely return to work.
Within our program, you will find a heavy emphasis on safety protocols, which outline our company-wide resources including tools, equipment and materials. The program provides the company’s succession plan, a communication strategy, as well as IT and data recovery.
We want to restore our business as quickly as possible to ensure we continue to support our client’s needs in a safe and efficient manner.
Dan Kapner
Attorney
Shapiro, Lifschitz & Schram, P.C.
Washington, D.C.
Natural disasters can strike at any moment and, unfortunately, have the ability to cause unprecedented damage to communities. Contractors should have an effective disaster recovery plan in place that addresses legal and insurance issues related to extreme or catastrophic weather events.
When creating a disaster recovery plan, project participants must evaluate the availability and scope of insurance policies in place, including property, casualty, builders risk and other policies; the scope of coverage must also be determined, including whether the policies cover wind storm and flood damage, business interruption losses caused by delays and how project participants will collect and preserve materials necessary to substantiate claims.
In addition, project participants must have an understanding of contractual rights and obligations if a natural disaster occurs. It is critical that contractors carefully review the particular terms of their construction contracts to identify applicable provisions or relevant to extreme or catastrophic weather events (such as delays, increases to costs of the work, claim submission requirements and disputes), as well as understand their rights and responsibilities so they are best equipped to get the project back on track.
John Reyhan
President
Manhattan Construction Company
With three full-service offices in hurricane zones, Manhattan’s disaster recovery plan has been put to the test on several occasions. In the case of hurricanes, basic protocols include:
Phase 1: Hurricane awareness. Six days in advance of landfall, when the path of the Hurricane shows potential to strike an operational area, our team initiates planning to secure operations. This advanced preparation provides our team members valuable time to secure their homes and make safety plans for their families.
Phase 2: Hurricane watch. 24-36 hours in advance of landfall, phone lines are transferred outside of the affected area. A pre-storm communication protocol is issued through multiple channels (cell, email, landline, and Zello). Reporting is established to know the location and safety status of every salary and hourly team member.
Phase 3. Hurricane warning. 12-24 hours in advance of landfall, operations are secured. The safety lead issues notices for Phase 4 action and provides NOAA storm updates every few hours. The team evaluates post-storm damage potential and recovery options.
Phase 4. Damage prevention. 12 hours in advance of landfall, supervisors lockdown operations and leave the area.
Post-storm. Confirm the safety of our team members and their families. Assess damage and needs.