Legal and Regulatory

Covenant of Good Faith and Fair Dealing Applied to Pass-Through Agreements

The legal practice every subcontractor should know before entering an agreement with a general contractor and building owner.
By Scott D. Cessar
May 30, 2023
Topics
Legal and Regulatory

Pass-through claims are claims by a party that has suffered damages but does not have a contractual relationship with the entity that caused the damages. In the construction industry, subcontractors commonly have claims for additional costs based on actions or inactions by the owner. However, since the subcontractor is not in privity of contract with the owner, it has no direct cause of action against the owner other than, perhaps, on a nongovernment project, a lien claim. In such cases, subcontractors may seek to pass the claim through the general contractor, who is in privity with the owner, to the owner.

Indeed, many construction contracts require the subcontractor, in such cases of owner-caused damages, to pass the claim through the general contractor to the owner. And since the harm visited on a subcontractor by the owner usually also affected the general contractor, the subcontractor’s claim is packaged together with the general contractor’s claim, which is usually greater, for presentation to the owner and, if not resolved, litigation with the owner.

AGREE TO AGREE

In these situations, the general contractor invariably controls the preparation, presentation and prosecution of the combined claim. The general contractor will select experts, engage counsel and interact directly with the owner and, if necessary, initiate and prosecute litigation.

For both general contractors and subcontractors involved in a pass-through claim situation, the best practice is to enter into a pass-through agreement, which sets forth the parties’ rights and responsibilities and addresses issues such as allocation of attorney and expert fees and litigation costs, routine information sharing, decision making as to settlement and allocation of settlement proceeds.

This is particularly important for subcontractors, because their claim is usually smaller than that of the general contractor, and subcontractors essentially find themselves riding the coattails of the general contractor. Some general contractors will actively involve and keep subcontractors abreast of developments in the prosecution of the joint claims; others will not and will pay token service to involving the subcontractor and then, after the case is settled or resolved, present the subcontractor with a breakdown showing the subcontractor’s share of costs and of the recovery from the owner to be paid to the subcontractor. This latter situation will likely produce a disappointing result for the subcontractor.

WORST-CASE SCENARIO

A recent case from New York, Rad and D’Aprile Inc. v. Arnell Construction Inc., demonstrates the worst-case situation of the general contractor abdicating its responsibilities to a subcontractor to whom it was entrusted with a pass-through claim. Arnell involved the circumstances of a classic owner-caused delay not barred by a no-damage-for-delay clause: the project was delayed/impacted because New York City did not have title to the project site, and, as such, the entire site was not available to the contractors for construction.

As such, the general contractor suffered delay damages as well as its subcontractor. Hence, the subcontractor passed its claim for delay damages through the general contractor, with the general contractor’s similar claim, to the city. The general contractor, however, failed to timely file an action against the city, resulting in the dismissal of the action and the subcontractor’s pass-through claim, and then the general contractor settled the claim without notice to the subcontractor and would not provide any compensation to the subcontractor from the settlement.

Subcontractor sued general contractor. General contractor sought to dismiss the action on a variety of grounds. The court denied the motion and, importantly, did not rely on a provision in the parties’ contract, but relied on a covenant implied by common law in contracts. This covenant is known as the covenant of good faith and fair dealing, which “embraces a pledge that neither party shall do anything which will have the effect of destroying or injuring the right of the other party to receive the fruits of the contract. It encompasses any promises that a reasonable person in the position of the promisee would be justified in understanding were included.”

Relying on the implied covenant of good faith and fair dealing, the court held that the general contractor’s failure to timely file litigation and to settle the case without consulting with the subcontractor and not sharing any of the proceeds constituted a breach of this covenant. Although this holding is based on common sense, it is important because the court relied on the implied duty of good faith and fair dealing to substitute and reach a just result where apparently express contractual duties of the general contractor to the subcontractor were absent.

SPELLING IT OUT

Arnell thus teaches that the best practice is to draft a thorough pass-through agreement that spells out the parties’ obligations to one another and the consequences otherwise. However, the implied covenant of good faith and fair dealing works as a check on roughshod practices, such as evidenced in Arnell, in order to incorporate promises that reasonable persons would expect to be included.

Another drafting suggestion gleaned from Arnell is to include a provision in the pass-through agreement which expressly states that the parties agree that they owe to one another the express duty of good faith and fair dealing. Such a provision would bolster the position of the subcontractor, and reasonable general contractors should not balk at its inclusion if, indeed, they are operating in good faith and because the duty is otherwise implied at law.

by Scott D. Cessar
Scott Cessar’s practice at Eckert Seamans Cherin & Mellott, LLC covers a broad range of civil litigation with a primary focus on construction law. He has extensive trial and alternative dispute resolution experience representing clients before state and federal courts, arbitration panels and mediators across the country. Scott’s construction law practice encompasses both public and private projects (commercial, heavy/highway, industrial, institutional and residential). Projects include hydroelectric plants, steel mills, bridges and highways, hospitals, office buildings, schools, laboratories, greenhouses, dams, pipelines, gas transmission facilities, water plants, sewer plants, mines, airports, glass furnaces, stadiums, hotels, pipelines, factories and process facilities and environmental remediation sites. Scott has handled all types of construction claims including delay, impact, loss of productivity, differing site condition, defective work, extra cost, architectural and engineering errors and omissions and overcharges, and bid and procurement protests; representing private owners, developers, public agencies, prime contractors, subcontractors, design professionals, equipment manufacturers and suppliers and sureties. Eckert Seamans Cherin & Mellott, LLC is a national law firm with over 375 attorneys located in offices throughout the eastern United States. The firm's clients represent nearly every facet of the economy, including multinational corporations, small businesses, nonprofit institutions, municipalities, government agencies and individuals. Scott D. Cessar can be reached at scessar@eckertseamans.com; 412.566.2581.

Related stories

Legal and Regulatory
Final Build America, Buy America Act Guidance Released
By P. Lee Smith and Greggory C. Maddaleni
This new guidance tightens U.S. content requirements for federally funded infrastructure projects, expands the definition of infrastructure and provides calculation methodologies for manufactured products.
Legal and Regulatory
A Look at Trending Legislative Changes Impacting Workers' Comp
By Rosanna Shamash
Could three recently enacted changes in New York State affect workers' compensation cases across the country for the construction industry?
Legal and Regulatory
How to Get the Most Bang for Your Buck Out of the Infrastructure Bill
By Rich Meene
The Infrastructure Investment and Jobs Act authorizes $550 billion in new funding for infrastructure projects. Here's how to position your company for success when pursuing these opportunities.

Follow us




Subscribe to Our Newsletter

Stay in the know with the latest industry news, technology and our weekly features. Get early access to any CE events and webinars.